Capping of Steel Structure Works of State Grid Shanghai EXPO Enterprise Hall
2009-9-25 13:41:39
      10:22 a.m. on July 26t, with slowly positioning of the last steel beam of the first zone flower shelf, the State Grid Shanghai EXPO Enterprise Hall contracted by  MCC Chenggong Shanghai Wuye, achieved the main steel structure capping, and the whole exhibition hall has been primarily completed.
     The State Grid Shanghai EXPO Enterprise Hall’s steel structure occupies the area of 2520 m2, and the steel structure’s total weight is about 2200 ton. There is triangle structure on both sides of the Enterprise Hall, and the top elevation is 19.7 m, and the top elevation of center magic box structure is 23.425 m.
    Since the formal commencement of the steel structure installation on May 25th ,Shanghai Wuye has made reasonable arrangement of the working procedure, coordinated the relative resources, and overcome the difficulties such as plum rain season, high temperature weather, in-turn construction and tight construction schedule to realize the main steel structure capping of State Grid Shanghai EXPO Enterprise Hall as per the milestones of schedule.  (By Tangyihui)
 
Page copyright MCC5 Group Corporation Limited(Shanghai) Powered by www.300.cn